A total of seven buildings form the new Maakri Quarter in the heart of Tallinn: a very striking multi-storey structure over 100 m high while surrounding historical buildings are being extensively renovated.
Maakri-Kvartal Business Complex

Fast high-rise construction progress with a well thought-out formwork concept

A total of seven buildings characterize the Maakri-Kvartal complex which is currently being built in the Estonian capital. The project comprises new high-rise buildings as well as restored architectural monuments and connects the historical heart with the newer district of Tallinn. PERI developed and delivered corresponding formwork solutions for the new structures as well as the renovation work. The PERI team has supported the rapid construction progress in particular with climbing technology for the city´s new landmark – a high-rise building with a height of more than 100 m.

Date
01. June 2017
Location
Tallinn, Estonia

##press.media.headline##

The following is an overview of the images contained in the press set

Centrally located in the heart of Tallinn, the new business complex will offer a total area of 36,000 m² after completion. In addition to office and commercial space, a conference centre along with several restaurants with corresponding outdoor areas are being realized – all with an unbeatable view of the city and the sea. Three very modern, newly constructed high-rise buildings will eventually completely merge with four historical structures from the early 20th-century that are currently being extensively renovated and expanded. The whole complex will subsequently present a very harmonious overall appearance.

Safe working at great heights – in wind and weather and limited crane use

The highest of the three new structures within the Maakri complex has 30 floors and thus is over 100 m high. For the first time in a decade, a high-rise building is being built in Tallinn that has exceeded this height. As the new landmark of the city, the building combines tradition and modernity.

The biggest challenge for the construction team was to maintain the very tight construction schedule while, at the same time, accommodating difficult weather conditions and limited crane and storage capacities in the densely built-up urban area. Furthermore, it was necessary to fulfil the high quality requirements of the client for the concreting work.

For the structural work, PERI engineers worked closely together with the site management in order to develop a comprehensive overall concept. PERI's climbing formwork solution greatly contributed, in particular, to minimizing crane utilization as well as accelerating the construction progress. The RCS Rail Climbing System was combined with the particularly efficient MAXIMO Panel Formwork to form corresponding climbing units. Through the rail-guided climbing procedure, these units were firmly connected to the structure at all times which made climbing fast and safe even during strong winds. The units were lifted to the next section using the mobile climbing hydraulics in 50 cm increments.

The MAXIMO Wall Formwork was positioned on a carriage and retracted by up to 90 cm for the reinforcement work. Due to the variable assembly options and 125 mm perforated grid of the climbing rails, the working platforms could be optimally adapted to suit the storey heights. In addition, a variant of the Rail Climbing Formwork was used as an enclosure and anti-fall protection for the gap-free continuous closure of the floors of the shell construction.

MAXIMO Panel Formwork was used not only on the climbing formwork but also for various other wall areas. With element heights of up to 3.30 m, together with the MX Tie Technology with ties installed from one side, valuable working time could be saved.

As the MX Tie Technology could be operated from one side only, no work was necessary on the setting side. In the process, the MX wingnut was fixed just once at the start of operations to the primary formwork and then the MX tie could be screwed in through the closing formwork into the wingnut – thus the anchor could be operated by one person and from one side during each forming operation. The conical-shaped tie rod did not require any spacer tube and cone which saved on materials as well as further time and effort. On the other hand, MAXIMO required up to 40 % less tie points than panel formwork systems using conventional anchor technology such as the Panel Formwork TRIO.

Last but not least, the wall formwork system ensured a clean concrete finish without any impressions from unused tie points. Furthermore, the centrally arranged tie points produced a regular joint and anchor pattern both horizontally and vertically. As a result, the construction team was able to meet the high requirements regarding the very best quality concrete surfaces.

The use of the SKYDECK Panelized Slab Formwork also helped the contractor and his team to maintain the required high safety standards. SKYDECK made a convincing case with its minimum of different, very light system components along with a systematic assembly sequence. The panel size indicated the support position whereby previous configuration was not necessary.

Apart from the development and delivery of the formwork solution, PERI´s range of provided services also included on-going advice and consultation on the construction site. The technical expertise, special know-how and the professional on-site support through a PERI supervisor saved valuable time on the jobsite.

The Maakri Quarter

For the planning of the Maakri Quarter, renowned architect Rasmus Tamme was tasked to seamlessly integrate the new buildings into the historical environment. The new structures are characterized by a strong, clear, minimalistic geometry – the architect made no attempt to copy the form of the historical buildings. Nevertheless, the past, present, and future came together to form a coherent whole.

The 110 m high multi-storey building is a new landmark in Tallinn. Up to now, the Swissôtel twin towers and Tornimäe 5 structure have dominated the skyline of the city. In future, the new 30-storey tower will complement this silhouette. Open glass fronts, a well-designed square as access to the new Maakri Quarter and inter-connecting inner courtyards make the complex a particularly successful mix of old and new.