SMCC Rapid P0001 RFCC Unit, Pengerang, Johor

Project data

Location: Johor, Malaysia

SMCC Rapid P001 RFCC Unit is part of the Petronas Rapid Project Package 1.  The tower standing at 30m high.

Requirements

Provide working platform for column at every 2m interval of total 30m in height for rebar installation and concrete casting.

Customer

SMCC Malaysia Sdn Bhd

Customer's benefit

  • Inherent safety of the product and lightweight of material improve the speed of erection.
  • Flexibility of the PERI UP system allowed the scaffold and shoring progress simultaneously.
Mr. Richard Vergara
Deputy General Manager

There are many shoring systems and lot of working scaffoldings on the market.  But PERI UP is the only system which equally satisfies both aspects.  In particular, the high load-bearing capacity impressed me a lot.

PERI solution

  • Column Scaffold
  • Shoring
  • Column