Project data

Location: Pengerang, Malaysia

This tower is part of the Petronas Rapid Project in Pengerang. The tower has a diameter of 7.65m and is 65m high.  Our customer, Toyo Engineering, are undertaking Package 5 and needed an engineered solution to overcome multiple obstructions to allow access for insulation works.

Requirements

Provide working platform for every 2m interval of total 65m in height for insulation projects.

Customer

Consortium of Toyo Engineering Corporation and Toyo Engineering & Construction Sdn Bhd

Customer's benefit

  • PERI UP was selected due to the inherent safety of the product and lightweight of materials.  The engineered solution enabled fast and safe erection times.
  • Weatherproof encapsulation was supplied consisting of a Monarflex sheeted temporary roof erected using aluminium beams.  The elevations were also clad in Monarflex sheeting.
  • 3D modelling helped to expedite the material planning and demonstrate the design.
Mr. Mikihiro Shiraishi
Site Services Manager (Rapid SCC Project)

The cooperation with PERI has proven to its extremely satisfactory for Toyo and our client. Deadlines can be met at all times.  For me, PERI UP means quality and ergonomics not least because PERI UP Scaffold construction can be optimally adapted to ensure safe execution of the insulation work.

PERI solution

Engineered solution using PERI UP and including shoring to span obstacles.

PERI systems in use