RGT2 LNG Tank
Pengerang, Malaysia

The re-gasification terminal (known as RGT-2) is part of Malaysia's development plan to secure stable natural gas supply for the nearby refinery and Petrochemical Integrated Development (RAPID), Pengerang Co-generation Plan (PCP) and also to the Peninsular Gas Utilization (PGU) Grid. This LNG Tank will have the capacity of 5 million tons per annual and two 200,000 cubmic meter LNG storage tank

 

 

Location
Main Application
Water Retaining Structures
Project participants
Customer: Samsung C&T Corporation 

The Project

1 /
3
You can reply on PERI
You can reply on PERI

Detailed cycle planning with optimized system use

Project Information

Requirements
To withstand the pressure from within (outer tank diameter of 89.40m and the overall pouring heigh of 4.5m) when completed.
To be completed by April 2018.

Solutions
To provide a package of solutions consisting of formwork, scaffolding, logistical and technical services throughout the project.
In addition to the planning of formwork and scaffolding solution for the complex geometries and high loads, strict compliance of the construction schedule and staying within the planned budget.

Customer benefits
Reduced labour costs thanks to accelerated construction process
Compliance with high safety requirements
Manage to finish the entire wall casting in only 8 sequences.

Civil Manager
Civil Manager
Mr. Alex Seo
Civil Manager
We are satisfied with PERI formwork not only the material but also their continuous technical support at site. PERI system are versatile and easy to handle during assembly, jumping and rectifying.

Related Products

Are you working on a project like this?

Call us on + 60 (03) 7969 1088 to discuss your requirements further.