You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

KVMRT UDG Cochrane Station, Kuala Lumpur

Project data

Location: Kuala Lumpur, Malaysia

The Cochrane Station, is one of the SBK Line’s underground stations will take commuters to the most vibrant parts of Kuala Lumpur, while enjoying world-class metro facilities that will not only be functional, but also aesthetic in design.  

All seven underground stations will be constructed using the cut-and-cover method. For those in the Kenny Hill Formation, construction will follow the top down process while those in Kuala Lumpur karst limestone are designed for bottom-up sequence.

 

 

 

Requirements

  • to provide a complete solution starting with design, calculation, method statement for installation, logistics and an instructor on site to ensure the installation ran smoothly.

 

  • to provide an access for installation of cladding on ceiling and walls as the space below the working area was fully occupied by escalators.

 

Customer

Nanyang Tunnel Engineering Sdn Bhd

Customer's benefit

Safety, versatility and fast installation.

Mr. Raymond Tan
Senior Engineer

With PERI UP system scaffold, construction can be optimally executed in a safer manner, shorter time frame and lesser cost.  The partnership and the support has been absolutely phenomenal, the productivity and efficiency has all been met and our targers are on track.

PERI solution

  • The metal decking with anti-slip surface is providing an excellent working area with live load capacity of up to 200kg/square meter.
  • To supply a hatch 75x100 with a ladder for the access from one level to another.

 

PERI systems in use