Palm paper mill, United Kingdom

Project data

Location: King's Lynn, United Kingdom

Europe’s largest and most modern paper mill, 600 m long, 100 m wide and 30 m high

Construction period until opening: 2008 - 2009

Requirements

  • tight schedule
  • coordination of shell construction and machine assembly
  • shear walls with a thickness of 1.50 m to 2.00 m

Customer

Glass GmbH, Mindelheim, Germany

Customer's benefit

  • construction time finished three weeks before schedule
  • fast shuttering times
Palm Paper Mill Statement - Stefan Bucher, Construction Manager
Stefan Bucher
Construction Manager

In my opinion, PERI UP is two thirds faster than common scaffolding systems. On the one hand, we are able to erect it fast and safely, and on the other hand, we achieve an efficient construction sequence due to the flexibility and versatility.

PERI solution

  • optimally harmonised formwork and scaffolding solution
  • outside work scaffold for safe shuttering, reinforcement and pouring of the 9.90 m high walls
  • shoring for protruding site-mixed concrete slabs and as temporary support of the FT beams
  • scaffolding staircase access to the work places

PERI systems in use