Project data

Location: Kelana Jaya , Malaysia

Paradigm Mall is part of the RM1.8 billion dynamic integrated commercial development, for WCT's that comprises a corporate office tower, serviced apartments and a 4 star business class Premiere Hotel with 4,300 parking bays. WCT started the construction since 2013 for Tower A, B and now Tower D.

Requirements

The close coperation of all parties involved during the planning and construction time ensured rapid building progress. 

 

 

 

Customer

WCT Construction Sdn Bhd

Customer's benefit

  • fabrication of one standard storey per week
  • high safety level for the jobsite staff
  • crane-independent, all-weather work processes
Mr. Too Chan Yan
Project Manager

Once again, PERI has proved to be the correct partner for us.  Without its support, the project would not have been as successfully completed as it was.

PERI solution

  • Using the easy-to-install Trio panel formwork, short shuttering and striking times could be realised for the walls.
  • The storey slabs and beams were formed systematically with a special beam tableform with less components and less work